Yacyretá hydroelectric power transmission plant- 500 kv (LITSA)

Commissioning Party: Execution Committee for the Rincón Santa María-Rodríguez Interconnection

Location: Argentina.

Construction of a transmission line of 593 km, including a 500 kV single-circuit line of 508 km in length and a 500 kV single-circuit line of 85 km in length. Expansion of a transformer station with four fields of 500 kV, one 500/132/33 kV transformer with 300/300/100 MVA capacity, a new transformer station with six equipped 132 kV fields, and expansion of a transformer station with a field of 500 kV equipped with two 80 MVAr reactor banks.

Completion of the project: 2008

Continue reading

Edificios UTA/UTL

Comitente: Nucleoeléctrica Argentina S.A.

Ubicación: Buenos Aires, Argentina

Descripción: Provisión e instalación de dos generadores de vapor de 20 t/h, con sus respectivos sistemas de apoyo, para los servicios de calefacción, vapor de sellos y acondicionamiento, y dos compresores de aire seco
para instrumentación y servicios. Piping de sistemas auxiliares (antincendios, agua desmineralizada, aire,
agua de servicio, etc.)

Finalización del proyecto: 2010

Continue reading