Tratayen Gas Processing Plant
ARGENTINA
11,2
MMm3/d flow rate
2.200
tns of metal structures
500
tns of assembled structures
1.200.000
MAN HOURS
- PRINCIPAL: Transportadora de Gas del Sur S.A
- SEGMENT: oil and gas
- Beginning of the project: 2023
- Under Construction
Construction of a project in Tratayén, Neuquén, which includes the design, assembly and start-up of a gas processing plant that injects conditioned gas to Neuba II, Central West and GPNK pipelines.