Tratayén Compresor Plant
ARGENTINA
11
MMm3/d flow rate
+10
tns of metalic structures
310
tns of mechanical
assembly of equipment
500.000
MAN HOURS
- PRINCIPAL: Energía Argentina S.A.
- SEGMENT: oil and gas
- Beginning of the project: 2023
- Completed
Construction of a compressor plant located in Tratayén, Neuquén province, to increase the GPNK's transport flow. During its execution, a 15,000 HP turbo compressor was installed.