Sierra Chata Field Expansion
Gas Pipeline and Fiscal Metering Station
ARGENTINA
100
MMm3/d of flow rate
24
km in 24´´and 4 km in 16´´
300.000
MAN HOURS
- PRINCIPAL: Pampa Energía S.A.
- SEGMENT: oil and gas
- Beginning of the project: 2023
- Under Construction
Construction of a gas pipeline, surface facilities and a fiscal metering station (EMED). The pipeline has a total length of 24 km of 24'' and 16'' and the EMED has three exit lines, with a transport capacity of 100 MMm3/d at a pressure of 129 kg/cm2.