Vaca Muerta Oil South
ARGENTINA
437
km in 30”
+76
special crossings
- PRINCIPAL: : VMOS S.A.
- SEGMENT: oil and gas
- Beginning of the project: 2025
- Under Construction
The Vaca Muerta Oil (VMOS) Sur project entails building a 437 km (271 mi) pipeline with a 30-inch diameter, from Allen to Punta Colorada on the Atlantic coast in the province of Río Negro. The realization of a project of this magnitude must overcome technical challenges, including the execution of 76 special crossings. Two of these will be carried out using Horizontal Directional Drilling (HDD) technology. The mobilization of over 300 key heavy construction vehicles stands out as essential to completing the work within the scheduled timeframe.
Neuquén
Notas relacionadas
Techint y SACDE ya están construyendo el Oleoducto Vaca Muerta Oil Sur (VMOS)
VMOS S.A., el consorcio conformado porlas principales empresas de energía de Argentina , adjudicó a la UT Techint - SACDE la construcción del proyecto de infraestructura energética más significativo del país de los últimos 50 años.
VMOS: la UT Techint – SACDE realizó la primera soldadura automática en línea regular
El proyecto Vaca Muerta Oil Sur (VMOS) alcanzó un nuevo hito en las cercanías de Chelforó, provincia de Río Negro, Argentina. Allí se realizó la primera soldadura automática en la traza de 437 km de extensión.